Monthly Archives: January 2012

20th January 2012 No. 40 Brickwork Complete

Very exciting week – No. 40′s brickwork is now finished, and it is all ready for the balance of the roof and the cladding. We expect lots of progress over the next few weeks as No. 36 was at fix … Continue reading

Posted in Uncategorized | Leave a comment

13th January 2012 Brickie returns early to No. 40

There isn’t much to report this week as it’s still xmas holidays. Traditionally not much happens during January so we were pleasantly surprised to find the brickie had returned early and was working hard at No. 40. It looks like … Continue reading

Posted in Uncategorized | Leave a comment

30th December 2011 Fix Stage Completed at No. 36

We had a site meeting with TC today to go through the house for the fix stage. All the doors are in, benches (not granite yet), plaster complete etc etc Apparently the painter starts mid to late Jan 2012. That … Continue reading

Posted in Uncategorized | Leave a comment